Northeast Miller Road electric system relocation

Project updates

  • This project is complete.
  • Construction began in May 2018 and ended in August 2018.

Project Description

In conjunction with the City of Bainbridge Island’s Miller Road (Core 40) shoulder improvements project, PSE relocated a segment of our electric system from overhead to underground lines to make room for the City’s work.

Prior to electric work, our tree trimming partner Asplundh trimmed bushes along the project route as needed. Crews then installed a protective casing underground to house the new underground electric cable, installed the underground electric cable, and removed portions of the overhead electric system.