Project overview
This project took place along Agate Point Road Northeast between Northeast Dolphin Drive and Northeast North Street. This project was completed in 2022.
The project’s goal was to increase reliability by converting a section of overhead distribution line to underground in order to protect from falling trees. The majority of outages on this line in the last few years were caused by full trees falling through the overhead line.

Contact Us
Artemia Settle, Project Manager
1-888-878-8632
info@psebainbridge.com
Quick facts
- Relocated approximately two miles of overhead distribution line underground